Project Value: 1.6M

Date:  February 2023

Acting as the Principal mechanical pipe contractor. Fabrication & installation of 1.5km of 250mm & 100mm Pipe to support  and supply additional 50 MW  energy upgrade.   The project also consisted of a number of CLASS 300 & 600 high pressure gas pressure reducing stations that was manufactured and tested in their offsite fabrication shop.